PROJECT SCHEDULE

Construction began in May 2012 and is scheduled to be complete by November 2014. Construction activity will vary depending on the time of the year and weather conditions. In order to reduce impacts to endangered fish species, work within the Clackamas River is limited to 6-8 weeks each year, beginning in July. During the majority of the project, traffic will cross the river on a detour bridge located just upstream from the existing bridge. A separate downstream work bridge will aid in the demolition and removal of the existing structure. Additional project work includes retaining walls on each side of the river to accommodate the wider bridge and approaches.

 